Background of the Invention
This invention relates to fault protection arrangements for electric power distribution systems.
The protection of personnel and electric system components, such as generators, motors, cables and power conversion equipment from short circuit conditions and other system anomalies is essential for safe and reliable distribution of electric power. Power continuity may also be critical for vital loads within a system. Heretofore, hierarchical protective arrangements using mechanical circuit breakers and fuses have been designed to utilize downstream protective devices which open first in order to clear a fault in a downstream circuit segment. In such systems the response times are slow and many protective devices are required. Moreover, time coordination of protective devices is necessary and, where fuses are used, blown fuses must be replaced before the system is completely restored.
Summary of the Invention
Accordingly it is an object of the present invention to provide a fault protection arrangement for electric power distribution systems which overcomes the disadvantages of the prior art.
Another object of the invention is to provide a fault protection arrangement for power distribution systems which provides automatic fault isolation and automatic system realignment more rapidly and with fewer components than prior art systems.
These and other objects of the invention are attained by providing a fault protection arrangement in which a plurality of power source lines are connected to supply power to a plurality of load circuits in which each power source has a dedicated circuit breaker, sensor and fault controller and each load circuit has a dedicated fault controller and fault sensor and a line switching device without any energy dissipation or absorption components.
In accordance with the invention, detection of a fault by a load line fault controller produces a load fault controller command to the fault controller for each power source supplying power to the related load to open the associated circuit breakers, after which the faulted load circuit is isolated by opening the relevant load circuit dedicated switch and thereafter the power source circuit breakers are directed to close. If multiple buses connected to each other through bus cross ties are supplied from separate power sources, the connections between the buses are likewise opened, permitting power sources connected to the unaffected buses to remain in service.
Brief Description of the Drawings
Further objects and advantages of the invention will be apparent from a reading of the following description in conjunction with the accompanying drawings, in which:
FIG. 1 is a schematic circuit diagram illustrating the arrangement of a representative embodiment of an electric power distribution system arranged in accordance with the invention;
FIG. 2 is a schematic timing diagram illustrating the relation of the operating times for the various components of the system shown in FIG. 1;
FIG. 3 is a schematic circuit diagram illustrating another representative embodiment of the invention providing an alternate power source;
FIG. 4 is a schematic timing diagram illustrating the relation of the operating times of the various components shown in FIG. 3;
FIG. 5 is a schematic circuit diagram illustrating an alternate embodiment of the invention; and
FIG. 6 is a schematic timing diagram illustrating the relation of the operating times of the various components shown in FIG. 5.
Description of Preferred Embodiments
In the typical embodiment of the invention shown in FIG. 1, a control system 10 includes a plurality of power sources 12a, 12b . . . 12n supplying power through power source lines 14a, 14b . . . 14n to a bus 16 and a plurality of loads 18a, . . . 18n receiving power from the bus 16 through corresponding load power circuits 20a, 20b . . . 20n. Each of the power source lines 14a, 14b . . . 14n has a fault sensor 22a, 22b . . . 22n of a conventional type arranged to transmit a signal to a corresponding fault controller 24a, 24b . . . 24n in response to sensing of a fault such as a short circuit in the corresponding power line. Circuit breakers 26a, 26b . . . 26n are included in each of the power source lines 14a, 14b . . . 14n and respond to signals from the corresponding fault controllers 24a, 24b . . . 24n to open the circuit between the corresponding power source and the bus 16. Preferably each of the circuit breakers 26a, 26b . . . 26n is a fast acting, current limiting solid state circuit breaker to improve power continuity over the use of conventional circuit breakers.
Each of the load circuits 20a, 20b . . . 20n, on other hand, includes a simple switching device 28a, . . . 28n without any energy dissipation or storage device of the type required when interrupting a current carrying circuit. This permits the load circuit switching devices 28a, 28b . . . 28n to be small, fast actuating and inexpensive. These switching devices are opened in response to a signal transmitted from a corresponding fault controller 32a, 32b . . . 32n.
In order to control the opening and closing of the circuit breakers 26a, 26b . . . 26n and the switches 28a, 28b . . . 28n, a communication circuit 34 is connected to each of the fault controllers 24a, 24b . . . 24n and 32a, 32b . . . 32n to transmit command signals for the operation of circuit breakers and switching devices in response to commands from the various fault controllers.
In accordance with the invention, whenever any load line fault controller 32a, 32b . . . 32n receives a fault detection signal from a fault sensor 30a, 30b . . . 30n in a load circuit 20a, 20b . . . 20n, the fault controller transmits signals through the communication circuit 34 to the controllers 24a, 24b . . . 24n for the power lines 14a, 14b . . . 14n which supply power to the bus 16 to which the load circuit having the fault is connected. Those signals cause fault controllers 24a, 24b . . . 24n to open the corresponding circuit breakers 26a, 26b . . . 26n and thereby terminate the supply of power to the group of load circuits containing the load circuit with the fault. Upon receipt of signals through the communication circuit 34 that all of the power source lines have been opened, the fault controller for the load line having the fault opens the corresponding switch under a no load condition, thereby avoiding the necessity for energy dissipation or storage arrangements. As soon as the switch 28a, 28b . . . 28n has been opened, the corresponding controller 32a, 32b . . . 32n transmits a signal through the circuit 34 to the controllers 24a, 24b . . . 24n for the power source lines 14a, 14b . . . 14n, causing them to close the corresponding circuit breakers 26a, 26b . . . 26n supplying power to the bus 16 and to the unaffected load lines 20a, 20b . . . 20n.
FIG. 2 shows the timing of the operation of the various circuit breakers and switches in the embodiment of the type shown in FIG. 1. This example assumes that two power sources, designated source 1 and source 2, are supplying power to the bus 16 and that three loads, designated load 1, load 2 and load 3, are receiving power from the bus 16 and that the load line leading to load 2 develops a fault. In the illustrated operation sequence, the power source line and load line fault controllers detect normal signals from the fault sensors during the time period designated T.sub.1 and at the time T.sub.2 the load controller for the load 2 detects a fault and transmits a signal during a message transmission period T.sub.3 to the power source controllers to open the corresponding circuit breakers. At the time T.sub.4, the power source controllers receive the message to open the circuit breakers and command the circuit breakers to open, which takes place during a time interval T.sub.5. At the time T.sub.6 the power source controllers send a confirmation message to the load controller for the load 2 that the circuit breakers for the power supply circuits have been opened. These messages are transmitted during the time period T.sub.7 and received at the time T.sub.8 at which time the controller for load 2 commands the load 2 switch to open. Opening of the load 2 switch occurs during the time interval T.sub.9, after which the load 2 controller sends a reclose message to the power source circuit breakers to reclose at a time T.sub.10. Following a transmission time period T.sub.11, the power source controllers receive the reclose message and command the circuit breakers to reclose at a time T.sub.12. Closing of the circuit breakers 26 occurs during the time period T.sub.13 and power is restored to the remaining loads 1 and 3 at the time T.sub.14.
Except for the circuit breaker commutation period T.sub.5, each of the steps described above occurs in a fraction of a millisecond. The length of the circuit breaker commutation period depends on the type of circuit breaker and the circuit characteristics and this step, which may require several milliseconds, will dominate the sequence of events. Thus, the power interruption, fault isolation and power recovery take place in essentially the time that it takes to interrupt power in the power supply lines, the time required for the other steps in the operation being negligible. Using fast acting circuit breakers for the power supply lines permits minimum power interruption as a result of a fault thereby providing improved power continuity in comparison with conventional arrangements which use a hierarchical method involving mechanical circuit breakers and fuses which are typically coordinated with intentional delays to allow downstream devices to open before upstream devices. Eliminating these delays and avoiding the use of magnetically and thermally activated devices significantly improves power continuity while reducing energy passing through during a fault. If desired, a group controller 36 connected to a manual electric system control station 38 may be included in the communication circuit 34 to permit operator control of the system and to check the status of the fault controllers.
If a power source fault controller 24a, 24b . . . 24n in one of the power lines 14a, 14b . . . 14n detects a fault which may, for example, be in the power line itself or in the distribution bus 16, that controller commands its corresponding circuit breaker 26a, 26b . . . 26n to open and interrupt the power supply through the corresponding line. Any other fault controller 24a, 24b . . . 24n in the lines 14a, 14b . . . 14n detecting its corresponding power source supplying the fault will also act to open the corresponding circuit breaker 26a, 26b . . . 26n in the same manner. In the arrangement shown in FIG. 1, however, all of the loads which receive power from the bus 16 must remain powerless until the fault in the power source line or the distribution bus has been corrected.
In order to eliminate that problem, a multiple bus arrangement 40 of the type shown in FIG. 3 may be provided. In this arrangement a source power line 12a supplies power to the bus 16 which in tun transmits power to a plurality of loads 18a, 18b in the same manner described above. In addition, however, a second bus 42 receives power from the distribution bus 16 through a bus cross tie 60. An alternate power source is connected to bus 42 through a line 44 having a fault sensor 46, a fault controller 48 and a circuit breaker 50 of the same type included in the line 12a. If the distribution bus 42 is powered from distribution bus 16 through bus cross tie 60, then circuit breaker 50 can be in the open state. A vital load, for which continuous supply of power is essential, is not connected directly to the bus 16 but receives power from the second bus 42 through a load power line 52. The line 52 has a fault sensor 54, a fault controller 56 responsive to the fault sensor, and a switch 58 which are essentially the same as the fault sensors and controllers and switches in the load lines 18a and 18b. The second bus 42 is connected to the bus 16 through a cross tie line 60 having a fault sensor 62, a fault controller 64 and a switch 66 which are also similar to the fault control arrangements of the load lines 18a and 18b.
In normal operation, the power source line 12a supplies power to the buses 16 and 42 which are connected together through the cross tie 60. In the event of a fault in the bus 16 or the power source line 12a, the circuit breaker for the power source line 12a is opened by the corresponding fault controller 24a in the manner described above and, upon receipt of confirmation signals through the communication circuit 34 that all of the circuit breakers are open, the controller 64 causes the switch 66 in the bus cross tie line 60 to open. When the controller 48 receives a confirmation signal through the communication circuit 34 from fault controller 64 that the switch 66 has been opened, it causes the circuit breaker 50 to close thereby restoring power to the bus 42 and to the vital load.
FIG. 4 illustrates the time sequence of the events involved in the operation of the arrangement shown in FIG. 3. During the time period T.sub.1 all of the fault controllers detect normal signals from the fault sensors. At the time T.sub.2, the controller 24a for the power source line 12a detects a fault and commands the circuit breaker 26a to open, which occurs during the time period T.sub.3. At the time T.sub.4, the controllers 24a and 48 send open confirmation signals to the controller 64 which occurs during time period T.sub.5. At time period T.sub.6, controller 64 commands the cross tie switch 66 to open. Opening of the cross tie switch takes place during the time T.sub.7 and when the cross tie switch is open at T.sub.8, the controller 64 sends an open confirmation signal to the alternate power source controller 48 during a message transmission period T.sub.9. At the time T.sub.10, the alternate source controller 48 commands its circuit breaker 50 to close, which occurs during the time period T.sub.11, so that at the time T.sub.12, power has been restored to the vital load.
In the arrangement shown in FIG. 3, if the primary power source supplying power through the line 12a fails or is taken out of service for some reason, the fault controllers perform an automatic realignment of the system to supply the loads on the lines 18a, 18b and 52 from the alternate power source. For this purpose, when the sensor 22a in the line 12a detects a loss of power, the corresponding controller 24a commands the circuit breaker 26a to open and sends a close message to the alternate power source controller 48. The alternate power source controller then closes its circuit breaker to restore power to the loads.
The arrangement of the fault controller communication circuit 34 in FIGS. 1 and 3 as a ring circuit may, if desired, be replaced by a point to point, star, or any other circuit configuration which permits each controller to detect signals from all of the controllers and to supply signals to all of the controllers. If desired, the fault controllers may also be arranged to keep a historical log of fault locations and electrical system protective device status for maintenance and trouble shooting purposes. The group controller 36 and electrical system control station 38 shown in FIGS. 1 and 3 permit operator control of the electric power distribution system so that an operator at the central control station may receive fault indications from the various controllers and transmit appropriate fault controller commands. The group controller may also be used to check the status of the protective system and to provide the other fault controllers with new fault detection criteria or to disable automated system realignments. Moreover, the communication circuit 34 may be a physical connection, such as wire or fiber optic cable, or it may be a wireless connection. Each of the fault controllers requires a reliable power source for operation since the fault controllers must operate when the power sources have been disconnected.
Furthermore, the arrangement of the invention may be utilized with a single master fault controller rather than dedicated fault controllers for each protective device. In this case, the master fault controller is arranged to communicate with every fault sensor and every protective device. This significantly reduces the total amount of hardware needed to implement the protective system. A secondary or back-up master fault controller could also be provided for resiliency.
If desired, the communication circuit 34 connecting the various fault controllers shown in FIGS. 1 and 3 can be eliminated while retaining ability to automatically isolate faults but, without the communications system 34, automated system realignments cannot be effected. In the absence of a communication system, a load controller detecting a fault sets an internal flag to provide an open command to its switching device when its corresponding fault sensor indicates the circuit has been interrupted (i.e., denotes zero current). A power source fault controller detecting the fault commands its circuit breaker to open, then waits a short period of time and commands its circuit breaker to re-close. During that time interval the load fault controller detects the circuit interruption and commands its switching device to open. If the fault is upstream of a load, the circuit breaker recloses and the power source continues to supply the fault but the power source fault controller then again detects the fault and commands the circuit breaker to reopen. The power source fault controller then waits, realizing the fault has not been isolated, or continues to reclose and open for a predetermined number of attempts. This arrangement provides a simplified protective system while still assuring automatic fault isolation without the detriments of a conventional system taking into account the transient requirements of the system. In addition to eliminating the fault controller communication system, this arrangement does not require fault controllers to have knowledge of present and future system alignments.
In an alternate embodiment shown in FIG. 5, the fault controller arrangement may be implemented on a distribution bus level rather than the described source level implementation. The arrangement includes Bus #1 and Bus #2 connected by a bus cross tie line as well as circuit breakers 72a and 74a and controllers 72 and 74 associated with power source #1 and power source #2 respectively, and a controller 78 and a switch 80 associated with load #3. The bus cross tie line includes a circuit breaker 68a and a controller 68 associated with Bus #1 and a circuit breaker 70a and a controller 70 associated with Bus #2. In addition, a group controller 82 controls a separate communication circuit 84 for the controllers associated with Bus #2. Such an arrangement requires more fault energy dissipation or absorption capacity since, instead of providing one circuit breaker for each power source, circuit breakers are required for every potential incoming power path to a distribution bus or group of distribution buses. Although more circuit breakers are necessary with this arrangement, the fault controllers associated with the distribution bus or group of buses do not have to communicate with fault controllers protecting another portion of the system. This provides an advantage with electric power distribution systems which are spread out over a large area or are otherwise difficult to link through a communication system.
FIG. 6 illustrates the time sequence of the events involved in the operation of the arrangement shown in FIG. 5. The fault controllers detect normal signals from the fault sensors during the time period T.sub.1 and at the time T.sub.2, the load controller 78 for load #3 detects a fault and transmits a signal during a message transmission period T.sub.3 to the power source #2 controller 74 and Bus #2 cross tie line controller 70 to open the corresponding circuit breaker 74a and bus cross tie circuit breaker 70a. At the time T.sub.4, the controllers 74 and 70 receive the message to open the circuit breakers 74a and 70a and command the circuit breakers to open, which takes place during the time interval T.sub.5. At the time T.sub.6, the controllers 74 and 70 send an open confirmation message to the load controller 78 for load #3 that the circuit breakers for the power supply #2 and for the bus #2 cross tie line have been opened. These messages are transmitted during the time period T.sub.7 and received at the time T.sub.8 at which time the controller 78 for load #3 commands the load #3 switch 80 to open. Opening of the load #3 switch 80 occurs during the time interval T.sub.9, after which the load #3 controller 78 sends a reclose message to power source controllers 74 and 70 to reclose the circuit breakers 74a and 70a at time T.sub.10. Following a message transmission period T.sub.11, controllers 74 and 70 receive the reclose message at time T.sub.12. Closing of the circuit breakers 74a and 70a occurs during the time period T.sub.13 and power is restored to load #4 at the time T.sub.14. During the process, there has been no power interruption to loads #1 and #2.
Although the invention has been described herein with reference to specific embodiments, many modifications and variations therein will readily occur to those skilled in the art. Accordingly all such variations and modifications are included within the intended scope of the invention.